THE SUPERDOME IS 50 — AND NEW ORLEANS REFUSED TO REPLACE IT

NOV 10, 2026 · SPLASH · SOURCED FROM TFC STADIUMS · THE RECORD
The Caesars Superdome in New Orleans

THE BUILDING THAT SHOULDN'T STILL BE HERE. Every other stadium of its era is dust. The Pontiac Silverdome: gone. Giants Stadium: gone. The Georgia Dome, built nearly two decades later: gone. The Louisiana Superdome is still standing on Poydras Street after fifty years — and it's about to be there for at least thirty more.

In October 2025 the Saints and the state signed a lease through the 2035 season, with four five-year extensions that could stretch to 2055. That's an extraordinary lifespan for a 1970s building, and it didn't happen because the dome was perfect. It happened because New Orleans kept cutting into it.

WHY IT EXISTS. Before the Saints, a businessman named Dave Dixon was already trying to make New Orleans a major-league city. The Houston Astrodome had just opened and changed what a stadium could be — air-conditioned, enclosed, usable in any weather, and able to host far more than football. Dixon looked at it and thought: we can go bigger.

The politics moved fast. On November 1, 1966 the NFL awarded New Orleans a franchise. One week later, Louisiana voters approved a constitutional amendment creating the Louisiana Stadium and Exposition District, with a 4 percent hotel and motel room tax helping pay for it. Until the dome existed, the Saints played at Tulane Stadium — an 80,000-seat open-air college bowl that had already hosted three Super Bowls, and was still a 1920s building on a campus.

Where it went mattered as much as what it was. An early plan put an all-weather stadium in Eastern New Orleans. Future mayor Moon Landrieu pushed hard for downtown, and the site ended up on largely abandoned railroad land near Poydras and the Pontchartrain Expressway — tying the stadium to a broader remake of the corridor and an economy that could no longer lean on the port alone. The dome was conceived as urban infrastructure: stadium, convention hall, concert venue and tourism engine in one shell.

THE PRICE. Early estimates: about $35 million. By 1969, before major construction, projections were near $94 million. Opponents sued; the Louisiana Supreme Court let it proceed. Final construction came in at $135.5 million; with debt service and administration, total expenditures reached roughly $163.3 million. Which is why you'll still see both numbers cited — both are right, depending on what's being counted.

THE ROOF. This is the part that still deserves awe. The circular structure spans about 680 feet, covers 9.7 acres, and rises roughly 273 feet over the floor. It holds around 20,000 tons of structural steel.

The roof isn't a few big trusses. It's a lamella system — repeating steel members in a diamond lattice that spread load outward into a massive perimeter tension ring. That ring was assembled from 24 prefabricated sections, each about an inch and a half thick, welded together roughly 169 feet above ground. Because a bad weld there could threaten the whole roof, the welds were done under controlled conditions and x-rayed.

Then the operation that tells you the scale: on June 12, 1973, about 5,000 tons of completed roof framing were jacked down onto the ring. From that moment the roof and ring worked as one system.

And it had to be a clear span, because this was never a football-only building. Movable seating meant football, basketball, baseball exhibitions, conventions and concerts could all use the same floor. The air conditioning alone: about 9,000 tons of cooling capacity. Grass couldn't survive under an opaque roof, so the field was artificial turf — the original Monsanto surface was branded Mardi Gras, which is the most New Orleans thing in this entire article.

It opened August 3, 1975, almost nine years after voters authorized it. New Orleans had been awarded Super Bowl IX on the assumption the building would be ready; it wasn't, and the game was played at Tulane instead.

KATRINA. On August 29, 2005, the dome became something it was never designed to be: a shelter of last resort for roughly 30,000 people who couldn't evacuate. The images from inside are inseparable from the disaster.

But the engineering distinction matters. Wind stripped the roof's outer membrane — a post-storm report estimated about 70 percent of it failed — and water ruined ceilings, electrical equipment, broadcast systems and finishes. The steel dome did not collapse. Within weeks engineers concluded it was repairable.

That decision is the whole story. Louisiana could have used the disaster as the moment to start over. Instead it spent about $185 million — roughly $116 million FEMA, $41 million LSED, $13 million state, $15 million NFL — and reopened on September 25, 2006, thirteen months later, for the Saints' nationally televised game against Atlanta. Everyone remembers Steve Gleason's blocked punt. The more remarkable fact is that a 9.7-acre enclosed building hit by one of the worst disasters in American history was back in major-event operation in barely a year.

THEN IT KEPT GOING. By 2011, restoration and improvements totaled about $336 million. Between 2009 and 2010 more than 400,000 square feet of exterior siding was replaced with about 16,000 anodized aluminum panels, restoring the champagne-bronze skin. In 2011 the plaza level was rebuilt — the old multi-purpose geometry became a football-oriented bowl with roughly 3,400 seats moved closer to the sidelines. Champions Square opened outside in 2010, giving the dome a front door instead of a ring of ramps.

It still reminded everyone it was a machine. During Super Bowl XLVII in February 2013, a partial electrical failure darkened sections of the building and stopped play for 34 minutes. The investigation blamed a protective relay: a design defect, an inappropriate factory default trip setting, and poor communication between manufacturer and utility.

THE $560 MILLION ANSWER. By the late 2010s the real question was whether to keep renovating a building approaching fifty or build new downtown. Stakeholders studied it and chose renovation again. Trahan Architects was commissioned in 2017; the program was described as roughly $450 million when approved around 2019 and finished as a $560 million transformation, with the Saints contributing nearly $180 million and the LSED and state covering the rest.

The radical idea: remove the ramps. For decades those ramps ate the interior perimeter, moving tens of thousands of people between levels. High-speed escalators and elevators do that with far less floor area. Stripping out much of the ramp network reclaimed more than 100,000 square feet of public space and another 50,000 of back-of-house — without adding a foot to the footprint.

Three atriums went into the opened space, with champagne-colored aluminum echoing the exterior and curved geometry following the dome's profile. Twelve new passenger elevators and five ADA platform lifts. New circulation built before old systems came out, so the building could stay open through Saints seasons and COVID. Work finished ahead of the 2024 season, and in February 2025 the renovated dome hosted Super Bowl LIX — the eighth Super Bowl inside the building, the eleventh in New Orleans counting the three at Tulane.

THE NAME. It was just "the Superdome" for 36 years. Mercedes-Benz bought naming rights in 2011 for a decade; in July 2021 Caesars Entertainment took over on a 20-year agreement. The roof still needs attention — Hurricane Ida passed through in 2021 without significant damage, and a pressure-washer fire during roof cleaning a few weeks later caused only superficial damage. Compare that to 2005: the envelope that faced Ida was not the envelope Katrina hit.

SPLASH'S READ: The Superdome is the best argument in American sports that a building's value is its location and its bones, not its finishes.

Every city that tore down its 1970s stadium did it for the same reason: the suites were wrong, the concourses were narrow, the revenue didn't match new buildings. New Orleans had all of those problems and one advantage nobody else had — the dome sits within walking distance of the Central Business District, a mile from the French Quarter. Replace it and you either build on the same footprint (impossible without a two-year gap) or move it somewhere worse. So the city did the harder, cheaper, smarter thing: it hollowed the building out.

Cutting out the ramps to gain 150,000 square feet is the detail worth stealing. That's not decoration; it's the only way a 1975 building gets modern concourses without new walls. And the fact that they did it in phases, around football seasons, with COVID landing in the middle, makes it an operations story as much as a design one.

The steel is the punchline. Everything under that roof has been replaced — turf, bowl, skin, escalators, atriums, even the name on the door. The 5,000-ton lattice lowered onto its ring in June 1973 is still doing exactly what it was designed to do. New Orleans never had to replace the idea. It just kept rebuilding everything around it.

SHOP THE STORY ▸
Fanatics — Saints gear
Watch: TFC Stadiums. Sources & claims: TFC Stadiums (YouTube), "Why New Orleans Refused to Replace the Superdome." Construction figures ($35M estimate, $135.5M construction / $163.3M total, 680 ft span, 20,000 tons of steel, 5,000-ton roof lift on June 12, 1973), the $185M Katrina rebuild breakdown, the $560M renovation and the 2025 lease terms are as presented in the video and consistent with LSED and Saints disclosures.